AF FERRARI CASE STUDY
■The challenge was to have access to electricity swiftly to meet the business's start of operation target date AND to minimize the CO2 footprint of the facility by incorporating a renewable energy plant (PV)
●Our Solution
■A turn-key microgrid which includes PV & BESS.
■The facility will be connected to the main grid in the future but it will only draw energy if needed to offset peak demand in case the PV plant is unable to provide sufficient energy to meet demand.
●Project Name: AF FERRARI
●Application: Microgrid with BESS, PV Plant and Genset 500kw-500kwh
●Scope of Supply
■BESS Station: Transformer, Power Conversion System, Auxiliares for PCS system, Microgrid-BESS Main Control System
■Batteries System: Container, Auxiliares for BESS system, Racks batteries
|
|
[ Microgrid ][ BESS Station ][ Transformer ][ Power Conversion System ][ PCS system ][ Microgrid-BESS Main Control System ][ Batteries System ][ Container ][ BESS system ][ Racks batteries ] |
|
Case Study |
|
|
|
Please see the document for details |
|
|
|
|
|
|
|
English Chinese Chinese and English Japanese |
|
2023.02.07 |
|
|
|
|
|
286 KB |
- +1 Like
- Add to Favorites
Recommend
All reproduced articles on this site are for the purpose of conveying more information and clearly indicate the source. If media or individuals who do not want to be reproduced can contact us, which will be deleted.