This instruction sheet will address “Accurate and proper installation”. The following tolerances are absolutely critical for good gravity flow results. These tolerances should be specified at the project development stage, included in the documentation for the installation pricing stage, included in the labor contract, reviewed at installation start up, and checked upon completion, prior to system sign off. We recommend the use of a transit or laser level to achieve these results.
● Rail must be installed at the specified slope for the application. The most common pitch used are 3/8” and 7/16” per foot, however refer to Interroll’s system drawing for the specific project or call Interroll for confirmation. The slope must not deviate from a true pitch line by more than 1/16”.
● Beams supporting the rail must be adjusted or shimmed so that rails within a lane do not deviate from level by more than 1/16”.
● Rails must be installed so that from front to rear of the system, the rail does not deviate from a true line by more than 1/16”.

Interroll

Pallet Flow

More

More

User's Guide

More

More

Please see the document for details

More

More

English Chinese Chinese and English Japanese

20 June 2008

1.2 MB

- The full preview is over. If you want to read the whole 22 page document,please Sign in/Register -
  • +1 Like
  • Add to Favorites

Recommend

All reproduced articles on this site are for the purpose of conveying more information and clearly indicate the source. If media or individuals who do not want to be reproduced can contact us, which will be deleted.

Contact Us

Email: