Test Procedure for the NCD57253GEVB Evaluation Board
●Test 1: Continuity test
■Power up Voltage sources
■Measure input currents – value must be lower than 10mA per channel
●Test 2: Functionality / Setup Test
■Power up Voltage sources
■Power up Signal Generators
■Check input Current - value must be lower than 10mA per channel
■Check A and B Currents - value must be lower than 50mA per channel
■Check input signals – signals need to be in opposite phase without deadtime
■Check output signals – output signal must be in phase with input signal with 100ns delay maximum
|
|